Projects for the electric power industry
Project documentation for the 2x400 kV S/S Ernestinovo - S/S Pécs transmission line, section: Ernestinovo - state border
Nominal voltage |
400 kV |
Section length |
44 km |
Number of towers
- suspension
- tension |
90
27 |
Total |
117 |
Average span |
376 m
(without connection span) |